Changing Contractor

Description

Changing Contractor

Required Documents

  1. Commissioning from the Owner
  2. Letter from the consultant explains(the required amends and completion rate)
  3. Disclaim from the previous contractor
  4. The new Contractor contract
  5. Letter from the consultant supervision
  6. A copy of Land scheme
  7. A copy of the previous building license
  8. A copy of consultant license
  9. A copy of Contractor's license1
  10. Application of full structural audit for the project (copy)1
  11. Fees according to regulations

Procedures

  1. Visiting customer service to determine the change application type
  2. Attach the documents with the application
  3. Payment of the prescribed fees
  4. Get the transaction

Service Fees

Description Payment Site Amount
Fees Department Funds 500 AED+ 100 AED
Fees Department Funds Administrative fees 40AED