Building license

Description

Get the print of sub-contract

Required Documents

  1. letter from the consultant clarify the required as sample
  2. Commissioning from the Owner as sample
  3. Land scheme (valid)
  4. A copy of consultant license (valid)
  5. A copy of donation (for Sheikh Zayed projects program)
  6. A copy of the initial scheme(architectural)
  7. Fees according to regulations
  8. AutoCAD CD initial architecturalSecond: Final Project
  9. initial approval (including all documents in the preliminary)
  10. Supervision letter as sample
  11. Contractor's contract
  12. consultant's contract
  13. A copy of contractor's license (valid)
  14. copy of the contractor and consultant registration (for Sheikh Zayed projects program
  15. Two geometric schemes for the final (architect - structural - plans (EMP)
  16. No Objection from Electricity , Water and Communication
  17. Approved applications according to electricity and telephone plans1
  18. Civil Defense approval of plans in case of (industrial - Commercial Residential)1
  19. soil test1
  20. construction accounts (calculation memorandum + sample of structural analysis)1
  21. Prevention and safety clauses for houses1
  22. AutoCAD CD for the final schemes

Procedures

  1. Complete the required documents
  2. The transaction submitted to the receptionist - customer service with Payment of the prescribed fees.B) final approval:
  3. After the initial approval ,required documentsshall be completed
  4. submit to Customer Service
  5. Refer to the structural audit department
  6. In case of Notes it is referred to the Consultant for amendment
  7. After final approval by the structural audit engineer the prescribed fees are calculated and referred to the Department of Licenses
  8. Building license will be approved by President of the Department of Licenses - Head of the Department of Engineering Affairs - Director General of the Municipality

Service Fees

Description Payment Site Amount
Fees Department Funds Ground housing 200 AED
Fees Department Funds 300 AED Ground housing+1
Fees Department Funds 500 AED Commericial ground housing +4
Fees Department Funds 1000 AED Commericial ground housing +4 or more
Fees Department Funds Industrial 1000 AED
Fees Department Funds Consultant 5000 AED
Fees Department Funds License fees are calculated according to the list of charges
Fees Department Funds Administrative fees 40 AED